Maintenance work began at Surinameplein
◆1 source
Large-scale maintenance work reportedly began at Surinameplein in Amsterdam on 16 November 2026. The entire asphalt structure, including its foundation, is to be replaced in three phases over almost a year. Preparatory work was underway, with demolition scheduled to begin the following week. Car traffic heading to the city centre has been diverted, while traffic controllers have dealt with congestion and frustrated motorists. Trams are being kept in service, and cyclists can pass around the work area; pedestrians have to take a detour.
The work is being carried out at the same time as work on the Overtoomsesluis, with the stated aim of reducing the overall disruption. The first phase is due to finish in March 2027, and the full project is expected to run until October 2027.